Deck Footing Concrete Calculator

Calculate concrete for cylindrical deck piers, with an optional rectangular base per footing. Enter dimensions from your project plan to get concrete volume and whole bags.

Metric unit converter

Convert your measurements into the units shown on the calculator, or convert a result to metric.

Project measurements

Material estimate

Concrete bags
18
Concrete before allowance
9.425 ft³
Concrete per footing
2.356 ft³

How the estimate works

  1. Identify each part of the footing

    Use the specified inside diameter of a round form and the height of its pour. For a rectangular base, enter its length, width, and thickness. The round height is measured above the top of that base, so the shapes meet without overlapping in your estimate. Use a zero base depth if you are pouring only a cylinder. Irregular, tapered, and bell-shaped bases need separate geometry.

  2. Calculate the cylinder

    Divide the diameter by two to get the radius. The cross-sectional area in square inches is π × radius². Multiply by height in inches to get cubic inches. Because the diameter is squared, doubling a form diameter quadruples the volume at the same height. Measuring a hole at only the narrowest point can understate the material if you are pouring directly against excavated soil.

  3. Add the base and footing count

    Multiply base length × width × thickness, then combine it with the cylinder volume. Divide cubic inches by 1,728 to convert to cubic feet. Multiply by the number of equal footings, or run the calculation for each group if the dimensions change across the deck. Combine volumes before rounding when you can share mixed material across forms.

  4. Use label yield for the order

    Apply the allowance to the combined volume and divide by the cubic feet the product yields per bag. Round up to whole bags. If the bag or data sheet lists liters, convert those to cubic feet or use the metric helper. If buying ready-mix, divide cubic feet by 27 to get cubic yards and confirm the supplier’s order increments.

Worked example

Four cylindrical footings are each 12 in across and 36 in high, with no rectangular base. One has a radius of 6 in and a volume of π × 36 × 36 ≈ 4,071.5 in³, or 2.356 ft³. The four together need about 9.425 ft³. A 10% allowance increases that to 10.367 ft³. At 0.60 ft³ per bag, that is about 17.28 bags before rounding, so buy 18.

Footings
4
Pier diameter (in)
12
Pier height above base (in)
36
Base length (in)
16
Base width (in)
16
Base thickness (in, 0 if none)
0
Yield per bag (ft³)
0.6
Extra material (%)
10

Reference table

Example project with one input varied; other settings stay as shown above
Pier diameter (in)Concrete per footingConcrete bags
81.047 ft³8
101.636 ft³12
122.356 ft³18
164.189 ft³31

Common mistakes

How much extra should I buy?

For clean, measured forms, 5–10% extra is a planning starting point for handling losses and measurement variation. An irregular excavation can require more, especially if its walls cave or flare. Estimate that geometry explicitly when possible. For separate pours, calculate each batch’s whole-bag requirement if leftovers cannot be used at the next footing. Confirm the yield printed on the exact mix you plan to purchase.

Before you order

Make a footing schedule with one line for each group of identical forms. Record form diameter, height above any base, base geometry, and quantity. A corner near sloping ground may use a different form height from the other locations. Subtotal each group in cubic feet, then identify which forms will be filled in the same session. Use combined volume for shared batches and separate bag counts for batches that cannot share material.

Compare bag handling and supplier delivery before settling on a purchase format. Eighteen 80 lb bags have a dry package weight of 1,440 lb, even though the estimated yield is measured in cubic feet. Check safe transport capacity with the vehicle manufacturer and discuss bulk quantities with the supplier when appropriate. The same concrete volume can be practical in one setting and awkward in another because of site access, equipment, or the number of separate pours.

Check actual form IDs and measured inside dimensions after placement. A form labeled with a nominal diameter may vary by product. If a form ends above grade, measure to the actual top of the planned concrete pour. Record any separate footing sections that the calculator cannot model directly and add their volumes to the project total before rounding to an order quantity.

Sources and assumptions

  • Volume comes from an inside cylindrical diameter plus an optional rectangular base with no overlap.
  • The default 0.60 ft³ bag yield matches an example in the QUIKRETE Concrete Mix technical sheet. Confirm the specified footing dimensions and your product’s yield.

Read the inside dimensions of the form

Use the inside diameter of the tube or form and the height it will actually hold. For an excavation poured without forms, measure the width at several depths. A straight cylinder is a useful approximation only when its cross-section stays reasonably consistent.

Treat footing schedules as separate pours where necessary

A stepped site can have several footing groups. Check whether the rectangular bases and cylindrical piers will be poured together. If the same mix cannot be shared between batches, round the bag count within each batch. Keep the unrounded volume per group to share with the supplier.

Another project to check

Two 10 in cylindrical piers rise 24 in above separate 18 × 18 × 6 in rectangular bases. Compare both shapes in a single takeoff using the label yield shown.

Concrete bags
11
Concrete before allowance
4.432 ft³
Concrete per footing
2.216 ft³

Frequently asked questions

How many bags fill a 12-inch form?

At 36 in high, one 12 in form takes about 2.356 ft³ before allowance. At 0.60 ft³ per bag, that is four bags without allowance or five with 10%.

Is a Sonotube measured by radius or diameter?

Enter the inside diameter. The calculator divides it by two to get radius for the volume formula.

What if the piers are different heights?

Calculate each group of matching dimensions separately. Add the cubic-foot volumes before applying one allowance if they will be part of a single pour.

Does this determine the footing size my deck needs?

No. Enter dimensions from your project plan or qualified designer and verify local requirements.

Can I use this for a bell-shaped footing?

The model covers a cylinder and an optional rectangular base. Calculate a flared or proprietary base separately from its known volume or product specifications.

This is a material estimate. Verify measurements, product coverage, and applicable local requirements before buying or building.

Related calculators