How the estimate works
Identify each part of the footing
Use the specified inside diameter of a round form and the height of its pour. For a rectangular base, enter its length, width, and thickness. The round height is measured above the top of that base, so the shapes meet without overlapping in your estimate. Use a zero base depth if you are pouring only a cylinder. Irregular, tapered, and bell-shaped bases need separate geometry.
Calculate the cylinder
Divide the diameter by two to get the radius. The cross-sectional area in square inches is π × radius². Multiply by height in inches to get cubic inches. Because the diameter is squared, doubling a form diameter quadruples the volume at the same height. Measuring a hole at only the narrowest point can understate the material if you are pouring directly against excavated soil.
Add the base and footing count
Multiply base length × width × thickness, then combine it with the cylinder volume. Divide cubic inches by 1,728 to convert to cubic feet. Multiply by the number of equal footings, or run the calculation for each group if the dimensions change across the deck. Combine volumes before rounding when you can share mixed material across forms.
Use label yield for the order
Apply the allowance to the combined volume and divide by the cubic feet the product yields per bag. Round up to whole bags. If the bag or data sheet lists liters, convert those to cubic feet or use the metric helper. If buying ready-mix, divide cubic feet by 27 to get cubic yards and confirm the supplier’s order increments.
Worked example
Four cylindrical footings are each 12 in across and 36 in high, with no rectangular base. One has a radius of 6 in and a volume of π × 36 × 36 ≈ 4,071.5 in³, or 2.356 ft³. The four together need about 9.425 ft³. A 10% allowance increases that to 10.367 ft³. At 0.60 ft³ per bag, that is about 17.28 bags before rounding, so buy 18.
- Footings
- 4
- Pier diameter (in)
- 12
- Pier height above base (in)
- 36
- Base length (in)
- 16
- Base width (in)
- 16
- Base thickness (in, 0 if none)
- 0
- Yield per bag (ft³)
- 0.6
- Extra material (%)
- 10
Reference table
| Pier diameter (in) | Concrete per footing | Concrete bags |
|---|---|---|
| 8 | 1.047 ft³ | 8 |
| 10 | 1.636 ft³ | 12 |
| 12 | 2.356 ft³ | 18 |
| 16 | 4.189 ft³ | 31 |
Common mistakes
- Using diameter as radius. The radius is half the diameter. Plugging the full form diameter into πr² makes the calculated cylinder four times too large.
- Including base depth twice. If your total height includes a rectangular base, subtract its depth before entering the cylinder height. Otherwise the layers overlap in the estimate.
- Using an example to size a footing. Example dimensions demonstrate the math. Your footing dimensions depend on approved plans and local requirements.
How much extra should I buy?
For clean, measured forms, 5–10% extra is a planning starting point for handling losses and measurement variation. An irregular excavation can require more, especially if its walls cave or flare. Estimate that geometry explicitly when possible. For separate pours, calculate each batch’s whole-bag requirement if leftovers cannot be used at the next footing. Confirm the yield printed on the exact mix you plan to purchase.
Before you order
Make a footing schedule with one line for each group of identical forms. Record form diameter, height above any base, base geometry, and quantity. A corner near sloping ground may use a different form height from the other locations. Subtotal each group in cubic feet, then identify which forms will be filled in the same session. Use combined volume for shared batches and separate bag counts for batches that cannot share material.
Compare bag handling and supplier delivery before settling on a purchase format. Eighteen 80 lb bags have a dry package weight of 1,440 lb, even though the estimated yield is measured in cubic feet. Check safe transport capacity with the vehicle manufacturer and discuss bulk quantities with the supplier when appropriate. The same concrete volume can be practical in one setting and awkward in another because of site access, equipment, or the number of separate pours.
Check actual form IDs and measured inside dimensions after placement. A form labeled with a nominal diameter may vary by product. If a form ends above grade, measure to the actual top of the planned concrete pour. Record any separate footing sections that the calculator cannot model directly and add their volumes to the project total before rounding to an order quantity.
Once the footprint and board direction are known, estimate deck boards and face screws separately. For a separate rectangular landing, estimate the concrete volume for the landing slab.
Sources and assumptions
- Volume comes from an inside cylindrical diameter plus an optional rectangular base with no overlap.
- The default 0.60 ft³ bag yield matches an example in the QUIKRETE Concrete Mix technical sheet. Confirm the specified footing dimensions and your product’s yield.
Read the inside dimensions of the form
Use the inside diameter of the tube or form and the height it will actually hold. For an excavation poured without forms, measure the width at several depths. A straight cylinder is a useful approximation only when its cross-section stays reasonably consistent.
Treat footing schedules as separate pours where necessary
A stepped site can have several footing groups. Check whether the rectangular bases and cylindrical piers will be poured together. If the same mix cannot be shared between batches, round the bag count within each batch. Keep the unrounded volume per group to share with the supplier.
Another project to check
Two 10 in cylindrical piers rise 24 in above separate 18 × 18 × 6 in rectangular bases. Compare both shapes in a single takeoff using the label yield shown.
- Concrete bags
- 11
- Concrete before allowance
- 4.432 ft³
- Concrete per footing
- 2.216 ft³
Frequently asked questions
How many bags fill a 12-inch form?
At 36 in high, one 12 in form takes about 2.356 ft³ before allowance. At 0.60 ft³ per bag, that is four bags without allowance or five with 10%.
Is a Sonotube measured by radius or diameter?
Enter the inside diameter. The calculator divides it by two to get radius for the volume formula.
What if the piers are different heights?
Calculate each group of matching dimensions separately. Add the cubic-foot volumes before applying one allowance if they will be part of a single pour.
Does this determine the footing size my deck needs?
No. Enter dimensions from your project plan or qualified designer and verify local requirements.
Can I use this for a bell-shaped footing?
The model covers a cylinder and an optional rectangular base. Calculate a flared or proprietary base separately from its known volume or product specifications.
This is a material estimate. Verify measurements, product coverage, and applicable local requirements before buying or building.